I have nearly 20 years of experience performing both placement and post-placement inspections of rebar, post-tensioning systems, concrete, masonry, etc. I’ve said it once and I’ll say it again: If structural engineers who specify epoxy for dowels and the like believe that the work is being done correctly then they live in a world unfamiliar to me. The key instructions to correctly epoxy in a dowel are either unknown to or widely ignored by contractors. You would be astonished at the number of so-caled epoxied dowels that I can pull out with one bare hand.
The following is of particular importance to a correctly epoxied dowel: The hole is cleaned with oil-free compressed air, brushed with a nylon brush, and cleaned again with oil-free compressed air. Generally speaking on a job site oil-free compressed air can only be obtained from a wet-dry vac or an air-compressor with the correct filters installed. Explaining to a contractor that the on-site air compressor can not be used for hole cleaning because the air contains oil that will act as a bond breaker between epoxy and concrete is like banging your head against a concrete wall and we haven’t even gotten to the brush part. A brush for cleaning the drilled holes is as elusive as a non-working rebar foreman; they rarely, if ever, exist on a job site.
I arrived at one particular job site last week to find the contractor in the process of placing #4 rebar dowels in 1.25” diameter drilled. The holes were drilled for 1” diameter SMOOTH dowels (the interface of an interior slab and an exterior slab where large trucks enter a service area). The contractor had no oil-free compressed air and no brush to clean the holes. On another job a pile cap had 18 #11 column dowels misplaced so all were cut off with a plan to drill and epoxy new dowels in the correct location. The contractor had no oil-free compressed air and no brush to clean the holes.
Over the years I’ve caught numerous contractors using the following procedure for placing epoxied dowels. 1) drill hole 2) hammer rebar into hole 3) squeeze epoxy onto the little mound of dust around the top of the hole. Seriously! I’ve also seen numerous dowels in place that have two different colors of epoxy on either side of the dowel/hole which means that the epoxy was squeezed into the hole without the mixing tube attached to the dispenser! I’ve seen numerous contractors attempt to mix the two parts of the epoxy mix on a board and then try to cram the “mix” into the hole with a little stick..
A couple of months ago I looked at a fix on a 300’ long retaining wall with #7 dowels at 6” and #5 dowels at 6”. When the foundation was placed (in three separate 100’ concrete placements) the dowels were placed in opposite faces of the wall and the EOR wanted new dowels #7 dowels epoxied in the correct face. I was able to dislodge 3 of the first 10 “epoxied” dowels I tested with two bare hands. I knew to test them because upon arrival to the site I bypassed the superintendent and went straight to the labor and asked how they installed all those dowels. This is a favorite tactic of mine, “How’d you do it?” I discovered that there was no on-site oil-free compressed air, no hole cleaning brush, and no correct size drill bit. OK, so I didn’t make it on that contractor’s Christmas card list.