roasted
Mechanical
- May 11, 2007
- 2
I have suggested to my company that we recover the blowdown flash steam by installing a flash vessel and pipe the recovered steam to the DA. The drum pressure is approx 1350 psig and the DA is approx 21 psig. The LP steam flow to the DA at present is approx 8t/h and the calculated flow of the flash steam will be approx 0.6t/h. Does anyone see a problem with this, does anyone know of a project of similar scale that has already been tried and tested, will the DA performance be affected in any way and what components are essential for safe operation?