wizster
Mechanical
- Apr 30, 2004
- 9
B31.1 clearly states that terminal points themselves (e.g., steam line connection on a header) are considered part of the boiler external piping. However, the code does not clearly define what material may be included in the terminal point.
My question is: can I include the counter-bored region of a weld preparation on the boiler fitting (Section I) side of the connection as part of the 'terminal point', or does the terminal point end at the fusion line of the weld?
The problem arose when NDE was performed on existing terminal welds. Low thickness readings were observed both sides of the weld, due to the counter-bore machined at the weld prep during original construction. Now what should we consider as the governing min T - Section I or B31.1 calculation? Min T is met on the fitting using a B31.1 calculation, but not by Section I (reason: boiler design temp at header is 1035 F, whereas piping design temp is 1005 F).
My question is: can I include the counter-bored region of a weld preparation on the boiler fitting (Section I) side of the connection as part of the 'terminal point', or does the terminal point end at the fusion line of the weld?
The problem arose when NDE was performed on existing terminal welds. Low thickness readings were observed both sides of the weld, due to the counter-bore machined at the weld prep during original construction. Now what should we consider as the governing min T - Section I or B31.1 calculation? Min T is met on the fitting using a B31.1 calculation, but not by Section I (reason: boiler design temp at header is 1035 F, whereas piping design temp is 1005 F).