Procedures of both the machines are approved. One machine say ABC(vendor) is approved with 4 sockets and the other(vendor) with 50 % sockets. So my concern here is the procedure which is approved with 4 sockets(tensioning values apllied are of the 4 sockets vendor) can be applied for the machine procedure which is approved with 50% sockets.Please note the values given by both the vendors are differnt.I hope i am not sounding confused