Zambo
Civil/Environmental
- Jun 5, 2003
- 697
On large diameter bored piles i typically see piles overcast (i.e. the concrete placed say 1.2m above cut off level) this pushes out any concrete mixed at the top with polymer and also covers the rebar at the top of the pile protecting it during excavation. This usually works out well because a pilecap could have a similar depth. But what about when i tie into a foundation slab without a deep pile cap (note i still need starter bars for columns above)? In that case unless i overfill before piling i cannot overcast. Can anyone suggest how to finish the pile so that i can minimise the work at cut off level and when work moves from the piling work to the foundation slab work.