Salvatio
Materials
- Oct 10, 2003
- 62
Dear all, I'm having some troubles, hope you guys could help me here. For current plant situation, each line has different capacity, with a ratio as below:
line 1 - 7
line 2 - 8
line 3 - 4
line 4 - 4.4
line 5 - 6
line 6 - 4
The process is from line 1 - line 2 - line 3 - etc. However, line 2 can provide WIP directly to either line 3 or/and line 4.
Problems start as soon as it reaches line 2. I've tried to arrange the production with smaller batch size, but still unable to provide any optimum solution. Is there any method to calculate or to simulate this? Thanks
line 1 - 7
line 2 - 8
line 3 - 4
line 4 - 4.4
line 5 - 6
line 6 - 4
The process is from line 1 - line 2 - line 3 - etc. However, line 2 can provide WIP directly to either line 3 or/and line 4.
Problems start as soon as it reaches line 2. I've tried to arrange the production with smaller batch size, but still unable to provide any optimum solution. Is there any method to calculate or to simulate this? Thanks