morgwreck243
Civil/Environmental
- Oct 23, 2013
- 21
I hope this is in the correct forum.
I am currently serving as the field engineer for a project where we are consolidating the bottom ash in the area onto the existing stockpile of bottom ash. Then we will be capping all of the waste material. Per the contract specifications, there is no density testing requirement, but only verification of compaction with a vibratory roller and lifts no thicker than 12 inches (loose). Then a proof roll inspection every 4 ft of compacted fill placed.
We've been having some problems with moisture levels so I was wondering if anyone has had any previous experience and could give some recommendations.
Our current plan forward is to start placing 6 inch lifts instead of 12 inch lifts. The thought being that this would allow for the material to dry out longer than the time it currently sits out.
Would simply allowing for the material to site & dry out longer be more helpful?
We have currently been placing the material at the top of the existing pile. Then spread out the material down the slope. Then the next day we would push the ash material where it needs to go.
--morgwreck243
I am currently serving as the field engineer for a project where we are consolidating the bottom ash in the area onto the existing stockpile of bottom ash. Then we will be capping all of the waste material. Per the contract specifications, there is no density testing requirement, but only verification of compaction with a vibratory roller and lifts no thicker than 12 inches (loose). Then a proof roll inspection every 4 ft of compacted fill placed.
We've been having some problems with moisture levels so I was wondering if anyone has had any previous experience and could give some recommendations.
Our current plan forward is to start placing 6 inch lifts instead of 12 inch lifts. The thought being that this would allow for the material to dry out longer than the time it currently sits out.
Would simply allowing for the material to site & dry out longer be more helpful?
We have currently been placing the material at the top of the existing pile. Then spread out the material down the slope. Then the next day we would push the ash material where it needs to go.
--morgwreck243