WARose
Structural
- Mar 17, 2011
- 5,593
I got a damaged masonry wall I need to replace (with a identical wall). It's between two elevated floors. Roughly 20' x 10' of wall. 10" CMU with brick veneer on outside. I normally have some kind of note that leaves bracing/support during construction to the contractor.....however in this case-with so much wall being replaced-I'm wondering if I can really get away with that? The wall removal won't cause any structural failure....it could disappear and the overall structure will be fine....except for the masonry above (which isn't much, maybe about 4').
So I guess my overall question here is: do I have a responsibility here as far as giving them (maybe) some type of temporary support plan (maybe a angle to act as a lintel or something during construction)? Or will the note I typically use be ok?
So I guess my overall question here is: do I have a responsibility here as far as giving them (maybe) some type of temporary support plan (maybe a angle to act as a lintel or something during construction)? Or will the note I typically use be ok?