Speckworm
Mechanical
- Feb 3, 2010
- 14
I was looking in older posts about repairs to PVs. Our vessel has been stamped and shipped, and now needs a bracket on a pressure-retaining wall. I think I understand it all now as follows:
ASME Code no longer applies, it is NBIC jurisdiction now.
Work must be performed by someone with an R Stamp.
NDE or pressure test must be performed when work is completed.
Both of the above under the approval of NBIC Inspector.
One question: Will the vessel actually require an R-Stamp? If so, what is the difference (if any) between welding a bracket to the vessel wall and say replacing a nozzle (penetration) that was damaged in shipment? Are they treated equally?
Metengr if you are out there your guidance would be most appreciated.
ASME Code no longer applies, it is NBIC jurisdiction now.
Work must be performed by someone with an R Stamp.
NDE or pressure test must be performed when work is completed.
Both of the above under the approval of NBIC Inspector.
One question: Will the vessel actually require an R-Stamp? If so, what is the difference (if any) between welding a bracket to the vessel wall and say replacing a nozzle (penetration) that was damaged in shipment? Are they treated equally?
Metengr if you are out there your guidance would be most appreciated.