If you're using the HydroCAD Chamber wizard, you can create two systems, one on top of the other. The lower system will have zero cover, and the upper system will have zero base.
Otherwise, you can use manual embedding:
1) Define the overall excavation volume.
2) Create the chamber storage for the lower chambers and set the embedding.
3) Create the upper chamber storage and set the same embedding.