I hope someone can help who is in the know. I have been looking at a number of 3.1 mill certificates against a BOM and found an issue (I think).
The material requested is S355JR+N but on the material certificate it just says S355JR. I have queried this back to the supplier and they said not all mills state the +AR or +N. Is this correct? I would assume if you ask for +N or +AR it should state it on the mill cert?