Hi all, first thread so be gentle with me please.
We have had a new CHP plant installed on site and during the testing an issue has arisen. When the CHP plant trips its 11kV breaker (during functional testing) an unrelated breaker also trips out on Bucholz trip. The CHP plant was wound down and not generating each time so there was no instant load transfer. The breakers are in the same room, on the same bus. The transformer whos breaker trips sits beside another transformer which also has a Bucholz relay- this does not trip. It's the same one each time. The breakers do not sit beside each other, one is panel 5, the other panel 7.
Does anyone have any ideas what could be up? We have Schneider coming on site as soon as they can free someone up, but it would good to get some ideas beforehand.
Thank you, Sean
We have had a new CHP plant installed on site and during the testing an issue has arisen. When the CHP plant trips its 11kV breaker (during functional testing) an unrelated breaker also trips out on Bucholz trip. The CHP plant was wound down and not generating each time so there was no instant load transfer. The breakers are in the same room, on the same bus. The transformer whos breaker trips sits beside another transformer which also has a Bucholz relay- this does not trip. It's the same one each time. The breakers do not sit beside each other, one is panel 5, the other panel 7.
Does anyone have any ideas what could be up? We have Schneider coming on site as soon as they can free someone up, but it would good to get some ideas beforehand.
Thank you, Sean