jdbpe
Structural
- Aug 4, 2005
- 28
I have a project with two old buildings (two stories) that share a common basement wall that consists of 20 inch thick stone rubble. The building to remain has a basement slab 12 feet below the first floor. The building to be demolished has a basement slab 8 feet below the first floor.
Our demo spec calls for removing the basement slab (higher slab) and three other perimeter walls of building and backfilling this area eith controlled fill. The common wall that will remain will now function as a retaining wall for the basement to remain.
Cores on the wall revealed that this wall could not function as a retaining wall.
How do we reinforce this wall? There are not any plans for future use of this lot that would allow us to design this wall, i.e. two story with steel columns and footings, load bearing etc and requirements for underpinning etc.
Do we require the contractor to drive sheet piling several feet from the wall and leave it up to the new owner to remove and build/reinforce as needed. Thanks
Our demo spec calls for removing the basement slab (higher slab) and three other perimeter walls of building and backfilling this area eith controlled fill. The common wall that will remain will now function as a retaining wall for the basement to remain.
Cores on the wall revealed that this wall could not function as a retaining wall.
How do we reinforce this wall? There are not any plans for future use of this lot that would allow us to design this wall, i.e. two story with steel columns and footings, load bearing etc and requirements for underpinning etc.
Do we require the contractor to drive sheet piling several feet from the wall and leave it up to the new owner to remove and build/reinforce as needed. Thanks