athomas236
Mechanical
- Jul 1, 2002
- 607
We are about to become involved with a CCGT project that will be built under winter conditions when the temperatures can fall to minus 50C.
We have considered storing the boiler pressure parts in heated warehouses and erecting the HRSGs in a building with a sliding roof or similar through we can lower the tube banks within supporting frames. The roof would be closed except for the times when pressure parts are being lowered into place.
Does anyone have anyother ideas.
Regards,
athomas236
We have considered storing the boiler pressure parts in heated warehouses and erecting the HRSGs in a building with a sliding roof or similar through we can lower the tube banks within supporting frames. The roof would be closed except for the times when pressure parts are being lowered into place.
Does anyone have anyother ideas.
Regards,
athomas236