Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations KootK on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Buried Tank Farm Piping

Status
Not open for further replies.

alexisa

Mechanical
Aug 5, 2003
2
Corrosion issues on buried piping sections up to 48" NB - Excavation costs for inspection of buried un-piggable piping are prohibitive long term. We are looking at ILI for parts of the buried piping we can access (tethered crawler tool via spool removal), but this is only for decision making further down the road. Total buried pipework circa 400m, up to 5m depth.

Options we are considering are: 1) Open up all buried piping sections in open trenches, 2) Going up and over tank bunds, then overground, 3) Excavate, inspect and replace buried sections with lined pipe, 4) Continue with periodic inspections. We are looking at a life extension of the tank farm facility until 2040 (20 yrs).

Option 1 is problematic for traversing earthen bund walls and maintaining containment during construction. Option 2 has hydraulic limitations and will likely increase opex for additional pumping. Option 3 may be prohibitive cost-wise for inconel or other pipeline trims. Option 4 (do nothing) is possible, however causes significant, on-going site access constraints (road crossings etc.) as well as control of works issues, and requires repetitive tank outages (loss of ullage) on an on-going basis.

From civil works perspective, Option 1 will be significant, particularly for bund wall crossings, but also as trenches will likely need retaining walls as well as major structures for crossing tank bunds. Option 2 will be least significant with structural pipe bridges and supports taking up more costs. Option 3 will also have significant excavation costs but not the civil element for option 1.

Does anyone have any experience or insights that may be usefull?

Thanks

 
Replies continue below

Recommended for you

It sounds that it's a good project with viable options.
May consider to have a Consultant look into these options with pro and con, as well as the alternatives or trade-off before the final decision.
 
I'd leave the post on and not decide for a while because among our members you may get a few prompt responses, but not every one looks here every day. It may take two weeks or more to do this.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor