stevenal
Electrical
- Aug 20, 2001
- 3,850
After a recent phasing snafu when interfacing with another utility, I learned that there are at least two philosophies. Our friends build their bus ABC north to south and east to west, and configure their reconfigurable transformers to fit the system. Our method is to build the bus to fit our ANSI standard transformers, and then make sure we hit the station correctly. Just thought I'd throw it out there for discussion. What do you do, why, and have you had this sort of communication problem?