MarteJupiter
Petroleum
- Mar 7, 2006
- 1
I am a new engineer. One of the wells during a zone completion the shut in pressure wasn't measured due to almost immidiate gas flow from the formation, now in order to calculate the size of choke and other facilities I need to have an idea of the surface pressure. I have my FRT report, that is giving me the P* pressure, no gradient available neither. How I can stimate the Shut-in pressure? or a THP "Tubing Head Preassure"?