mkaminski100
Petroleum
- Feb 9, 2009
- 2
Welding of no pressure pipework was completed to a set of WPSs / PQRs. After the work is completed, we were asked for additional weld tests. Vendor does not have the original test piece, therefore is suggesting two options:
1. Weld new coupon to supplied WPS and send it for testing which will be then added as an addendum.
2. Use new WPSs/PQRs, which they are preparing for similar job. These qualify to the same material and range, with number of additional tests. These would be used retrospectively, with the Record Book updated to reflect this.
I would highly appreciate if you could advise if any (or both) option is acceptable.
1. Weld new coupon to supplied WPS and send it for testing which will be then added as an addendum.
2. Use new WPSs/PQRs, which they are preparing for similar job. These qualify to the same material and range, with number of additional tests. These would be used retrospectively, with the Record Book updated to reflect this.
I would highly appreciate if you could advise if any (or both) option is acceptable.