EngDM
Structural
- Aug 10, 2021
- 389
Going to cross-post this thread over here as it's not necessarily just a SAFE issue but more of a theory issue.
thread803-523278 - Please lock the other one if similar threads are not allowed.
When designing a raft slab, is it possible to stiffen the slab with additional horizontal reinforcing to have the slab engage a wider strip of soil below my line load and thus lower the bearing pressure? I have an issue where my load exterior bearing walls are exceeding my factored bearing capacity due to how the load propagates thru the concrete down to the soil, but I have existing drawings of an identical building on the same site with the same bearing allowances, that was stamped and sealed. My counter argument is that for the slab to start engaging the soil further away from the load point, it would first have to deflect a bit which, soil deflection under load is a failure (settlement is a different animal). But it was suggested to me to stiffen up the slab to go from, for instance, 3' of engaged width to 4'.
I'm just curious as to what approach would be considered reasonable? I've tried playing around in SAFE by increasing reinforcing and it doesn't appear that it will help in any way; only changing slab thickness or subgrade modulus has any affect.
thread803-523278 - Please lock the other one if similar threads are not allowed.
When designing a raft slab, is it possible to stiffen the slab with additional horizontal reinforcing to have the slab engage a wider strip of soil below my line load and thus lower the bearing pressure? I have an issue where my load exterior bearing walls are exceeding my factored bearing capacity due to how the load propagates thru the concrete down to the soil, but I have existing drawings of an identical building on the same site with the same bearing allowances, that was stamped and sealed. My counter argument is that for the slab to start engaging the soil further away from the load point, it would first have to deflect a bit which, soil deflection under load is a failure (settlement is a different animal). But it was suggested to me to stiffen up the slab to go from, for instance, 3' of engaged width to 4'.
I'm just curious as to what approach would be considered reasonable? I've tried playing around in SAFE by increasing reinforcing and it doesn't appear that it will help in any way; only changing slab thickness or subgrade modulus has any affect.