I am Raja, i have some technical doubts ,i am working in 33/11 KV substation with 3 20 MVA(33/11.5KV) transformer
1) 11KV SWG SEC-A,SEC-B & SEC-C (three incomer & 2 Bus section scheme)
2) 5 MVAR capacitor bank for each 11KV SWG( SEC-A,SEC-B & SEC-C)
My doubt when incomer-1 in off condition bussection-1 closed and incomer-2 feeding the load of SEC-A & SEC-B ,so in this condition for power factor correction capacitor bank -2 is enough to connect in the bus or capacitor bank-1 also need to be connected to the bus?
please clarify the above issues
Thanks & Regards
Raja.P
I am Raja, i have some technical doubts ,i am working in 33/11 KV substation with 3 20 MVA(33/11.5KV) transformer
1) 11KV SWG SEC-A,SEC-B & SEC-C (three incomer & 2 Bus section scheme)
2) 5 MVAR capacitor bank for each 11KV SWG( SEC-A,SEC-B & SEC-C)
My doubt when incomer-1 in off condition bussection-1 closed and incomer-2 feeding the load of SEC-A & SEC-B ,so in this condition for power factor correction capacitor bank -2 is enough to connect in the bus or capacitor bank-1 also need to be connected to the bus?
please clarify the above issues
Thanks & Regards