I need to check an existing 8" thick two-way concrete slab for an eccentric distributed load of mechenical equipment of 60 PSF. The dead load of the slab is 100 PSF in addition to permanant dead load of 40 PSF. The total load on the panel is 200 Psf. It is a 24'x15' typical interior salb panel. The existing salb was reinforced with #4 @ 12" Each Way.
I have analysed the floor for its capacity using the direct design method of ACI, and found that the existing reinforcement is inadequate.
Is there any other way to check the existing salb for its capacity? whether my calculations are correct, or am I missign something?
Thanks for your time
sree