windrunner888
Civil/Environmental
- May 8, 2006
- 4
I am a little bit stuck on one of my project. The project is adding new post-installed rebars on existing round pier. When calculating its development length, what is cb? The definition of cb in ACI is the lesser of side cover (not governed in my case) and spacing of the bars being developed. But should it be the spacing of new bars and existing bars instead? Using the spacing of new bars gives me 5’ of development length, while spacing of new to existing bars gives me 18’.
The way I am thinking is that it should be like spliced bars, where the cb is taking the spacing of bar being spliced.
Any thoughts? Thanks in advance.
The way I am thinking is that it should be like spliced bars, where the cb is taking the spacing of bar being spliced.
Any thoughts? Thanks in advance.