Hello:
I would like to know which factors have you guys used in the past for Load Duration.
The 2004 -APA Concrete Forming Document states that I can use 1.625, but the ACI 347 says to use a 1.25.
I think that 1.625 is just high.
What do you guys think?
Thanks