Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

Centrifugal Pumps Switchover Guideline. (service to stand-by).

Status
Not open for further replies.

Kaadm

Mechanical
Jun 28, 2012
32
0
0
DZ
Hello,

I wonder what are the guidelines that specify the switchover frequency for a Service/Stand-by centrifugal pumps.

Many thanks,

Adem
 
Replies continue below

Recommended for you

That very much depends on duty, application and criticality of the supply from the pumps.

The actual frequency used should be based on the above and should include a MTTF analysis.

MTTF is Mean time to failure.[ul]
[li][/li]
[/ul]
 
As a basis you should start from the manufacturers recommended service interval so that one pump is being serviced / maintained whilst the other one starts its operating time / cycle.

Anything less than that is usually just something that develops over time in a company so that each pump is operated for equal periods over say a year.

So long as the standby is properly isolated / drained then there should be no bad effects on having a standby as, well, a standby.

My motto: Learn something new every day

Also: There's usually a good reason why everyone does it that way
 
Littleinch wrote:
"So long as the standby is properly isolated / drained then there should be no bad effects on having a standby"

In my experience the pump on "Stand-By" was not isolated and drained (unless it was in fact to be worked on or removed). The switchover frequency for a Service/Stand-by was part of the Start/Stop/Auto operation of the vast majority of the pumps in the Units. They were not taken Off line, they were only cycled off and left idle while the companion pump operated and maintained the system service. To do this the idle pump comes on and gets up to speed before the first pump is shut down. This results in a slight overlap of pump operation but no loss of production.

prognosis: Lead or Lag
 
I agree that that is how it often done, my point was that leaving the standby pump full of product and sometimes with the inlet valve open with just the discharge valve actuated was that you could get seal damage and leakage and potential for corrosion, settling of any solids and other issues associated with long term idleness. In that type of operation you probably want to look at quite regular change over of the duty pump - say at least once a week?

Depending if the service is continuous or intermittent will determine if the change over needs to be "bumpless" or not.

My motto: Learn something new every day

Also: There's usually a good reason why everyone does it that way
 
I appreciate your help Gents.

I would say that the switchover frequency is mostly based on the scheduled preventive maintenance (PMs) such as oil change

where the pump need to be out of service, However I believe that the frequency is certainly relative to the pumps

performance.Also it is rare to find the switchover frequency mentioned within the manual.

Most of the centrifugal pumps installed in petrochemical plant work with redundancy keeping the process system in continued

operation in case if the pump which is in service fail.

I still wonder what is the appropriate procedure with regard to the centrifugal pumps switchover frequency?

The standard API 610 is very rich of centrifugal pumps knowledges but the switchover frequency is not mentioned.

Thank you
 
"I still wonder what is the appropriate procedure with regard to the centrifugal pumps switchover frequency?"

I assumed that from the posts received so far that it would have been reasonably clear there is no "appropriate procedure", as it comes down to the application, the likely deterioration during service and plant history/ experience. If the pumps in question are in continuous operation and have a service life of 2 years between overhauls / service there wouldn't be much sense in rotating them every other day - however if the pumps run on and off all day there probably isn't any problem in rotating then each week or even each day or each start-up if it doesn't cause any start / operation problems- but entirely up to you, it's your plant and you have the information (or should have)on which to base any decisions.

It is a capital mistake to theorise before one has data. Insensibly one begins to twist facts to suit theories, instead of theories to suit facts. (Sherlock Holmes - A Scandal in Bohemia.)
 
Status
Not open for further replies.
Back
Top