I have a project that I am looking at for a client. The project consists of a renovation of an existing masonry building and turning it into a building that houses an ambulance company. The project was pitched as “we are just adding some openings in the exterior masonry walls:
On the surface that looks great until you start digging into the code (The code to be used for the building is IBC 2012 and ASCE7-10). Upon further review we are basically taking a structure that is Risk Category II and turning it into a Risk Category IV structure. Now, would an upgrade of the entire building be required or just the areas that I am modifying (poking holes into the wall)?
Now chapter 34 of the IBC deals with change of occupancy but it was noted in ASCE7-10 that they changed the Occupancy Category to Risk Category to avoid confusion…. so, I’m not quite sure how to handle this.
On the surface that looks great until you start digging into the code (The code to be used for the building is IBC 2012 and ASCE7-10). Upon further review we are basically taking a structure that is Risk Category II and turning it into a Risk Category IV structure. Now, would an upgrade of the entire building be required or just the areas that I am modifying (poking holes into the wall)?
Now chapter 34 of the IBC deals with change of occupancy but it was noted in ASCE7-10 that they changed the Occupancy Category to Risk Category to avoid confusion…. so, I’m not quite sure how to handle this.