Hi, I am new to MSP. I need help in creating Creating Different Calendar format for differnent tasks.
For my project, I have many different tasks going on at the same time for which working hours and working days are different. For eg :
1.Engineering work-
Days:Monday to Friday-
Date: Start 5th March 08- Finish: 30th September-09
Time: 8 to 5:30-1 hr lunch break between 12 to 1.
2. Offshore work
Days:Monday to Sunday (all 7 days)
Date: Start: 1st August 09- Finish: 15th September-09
Time: Throughout 24 hrs
How can I set up the calendar so that it calculates total number of days for task 1 and 2 ?
The problem which I am facing is that when I change calendar format for 1 task, it changes for the all the tasks in the project.
Any help would be greatly appreciated.
Thanks.
For my project, I have many different tasks going on at the same time for which working hours and working days are different. For eg :
1.Engineering work-
Days:Monday to Friday-
Date: Start 5th March 08- Finish: 30th September-09
Time: 8 to 5:30-1 hr lunch break between 12 to 1.
2. Offshore work
Days:Monday to Sunday (all 7 days)
Date: Start: 1st August 09- Finish: 15th September-09
Time: Throughout 24 hrs
How can I set up the calendar so that it calculates total number of days for task 1 and 2 ?
The problem which I am facing is that when I change calendar format for 1 task, it changes for the all the tasks in the project.
Any help would be greatly appreciated.
Thanks.