I am designing a small SS lift station with a grinder pump. After the pump, the line needs to go horizontal for 100 ft. before rising up 10 ft. I need to prevent the line from draining back into the sump. Can a check valve be used at the pump discharge? What about the settlement issue on the horizontal section of the pipe?