CTSeng
Structural
- Jan 21, 2003
- 125
Working with a fabricator that wants to do a CJP field welded flange moment connection with 2 separate backer plates either side of the beam web and no access hole thru the web at the top flange only. I know this is not in exact accordance with the procedure but seems reasonable. Should this be allowed in a non-seismic application?