angleburt
Mechanical
- Apr 13, 2008
- 9
I have a request to upgrade a standard controls enclosure to satisfy class 1 - Div 1 (actually it is for a project in India and their request is Gas Group IIA/B, Zone 1, T4, I interpret this to be class 1 - Div 1)
In the past, we have used enclosures with a purge (z-purge specifically), but for this application it is not desired.
Is it as simple as installing the components, (PLC, Relays, circuit breakers) into a Nema Type 7 enclosure, and using rigid conduit and appropriate rated fittings to make the connections to the equipment?
Thanks in advance
Angleburt
In the past, we have used enclosures with a purge (z-purge specifically), but for this application it is not desired.
Is it as simple as installing the components, (PLC, Relays, circuit breakers) into a Nema Type 7 enclosure, and using rigid conduit and appropriate rated fittings to make the connections to the equipment?
Thanks in advance
Angleburt