Hello, I am a Project Engineer managing a small amount of Masonry scope which is something I have never dealt with. Our sub let me know that the current plans have constructability concerns, as it wont be possible to place the masonry with the hooked downs as shown. Since I am not a structural engineer, does anyone have any ideas on how this design can be modified to make it constructible? The CMU blocks are 6" and we are in a seismic zone if this helps at all.