Beanbag1
Structural
- Mar 12, 2014
- 21
I am putting together a set of construction specs for a new 15-foot high building with 8-inch CMU exterior load bearing walls, with vertical reinforcing every 32-inches C/C, and I would like to know how many courses high can the blocks be laid before the contractor has to stop and wait for the mortar to cure, before continuing on up. I was told by another contractor that it's 8 courses and then wait 12 hours, but he doesn't recall where he got that information from. Can someone please tell me where in ACI 530 this is conveyed? Thanks.