tprofessional10
Civil/Environmental
- Apr 5, 2012
- 4
I apologize in advance if the question is somewhat remedial. This is not typically my field of expertise. However something has come up for me that requires some braced cut analysis...
I have been reading the previous posts, and it seems this issue is largely split on how to properly apply the surcharge load.
When designing for a cofferdam style shoring system (or any other temporary shoring system),
One must account for lateral soil pressure(rectangular distribution in fine soil), however lets say for example the contractor wants to use a large crane (200 ton) to work within the shoring system at a distance of X' back from excavation.
Question is do I simply use Q*H*k for this?
Q = vertical pressure
H = excavation height
k = active soil pressure coefficient
and furthermore, should it be multiplied by a factor of 2?
For simplicity:
Say the vertical pressure is 1900 PSF for the crane with a track length of 24' and width of 4' per track and the excavation is 20' deep with soil pressure coefficient = .39.
Would it then be
1900PSF * 20' * .39
Seems like this number is grossly large, especially if multiplied by 2.
Should it then be distributed over the entire wall of excavation to a PSF?
If so, should the smaller side of cofferdam (assuming a rectangular unit) be used to be conservative.
Where does the distance from the excavation come into play?
Is there a surcharge load that would be considered conservative for all cases that could be used in place of specific calculation of crane or any other equipment/spoils pile/etc for that matter?
Thank you in advance for your help!!
I have been reading the previous posts, and it seems this issue is largely split on how to properly apply the surcharge load.
When designing for a cofferdam style shoring system (or any other temporary shoring system),
One must account for lateral soil pressure(rectangular distribution in fine soil), however lets say for example the contractor wants to use a large crane (200 ton) to work within the shoring system at a distance of X' back from excavation.
Question is do I simply use Q*H*k for this?
Q = vertical pressure
H = excavation height
k = active soil pressure coefficient
and furthermore, should it be multiplied by a factor of 2?
For simplicity:
Say the vertical pressure is 1900 PSF for the crane with a track length of 24' and width of 4' per track and the excavation is 20' deep with soil pressure coefficient = .39.
Would it then be
1900PSF * 20' * .39
Seems like this number is grossly large, especially if multiplied by 2.
Should it then be distributed over the entire wall of excavation to a PSF?
If so, should the smaller side of cofferdam (assuming a rectangular unit) be used to be conservative.
Where does the distance from the excavation come into play?
Is there a surcharge load that would be considered conservative for all cases that could be used in place of specific calculation of crane or any other equipment/spoils pile/etc for that matter?
Thank you in advance for your help!!