seny
Structural
- Oct 21, 2007
- 33
Hi everybody,
I’m modeling 30 storey concrete building w/ shear walls lateral system and columns responsible only for gravity.
As per ACI 318 section 8.8 we top of columns to be modeled as fixed and release can be assigned to bottom of the column.
Is it appropriate way to model column in Etabs for service and ultimate stage – hinge at the bottom & fixed at the far end? So all the columns will have no release below the floor and hinge right above at all the point of column & slab intersection.
One more question, I need to transfer at the second floor elevation on of column to two adjacent columns over the bridge (transfer) beam. What is the best way (technique) to model transfer beam to two columns below connections in Etabs? In case two columns below, three columns above and beam have no releases – all the columns (below and above) fail b/c of transferred moment from the beam and required enormous sections, what is not the case in real life. Assign releases at the beam ends? In this case haw Etabs takes in consideration that in real life there are no released beam & column joints in monolithically poured structures?
I am sorry for long post.
Any input on these matters are highly appreciated.
Best regards.
I’m modeling 30 storey concrete building w/ shear walls lateral system and columns responsible only for gravity.
As per ACI 318 section 8.8 we top of columns to be modeled as fixed and release can be assigned to bottom of the column.
Is it appropriate way to model column in Etabs for service and ultimate stage – hinge at the bottom & fixed at the far end? So all the columns will have no release below the floor and hinge right above at all the point of column & slab intersection.
One more question, I need to transfer at the second floor elevation on of column to two adjacent columns over the bridge (transfer) beam. What is the best way (technique) to model transfer beam to two columns below connections in Etabs? In case two columns below, three columns above and beam have no releases – all the columns (below and above) fail b/c of transferred moment from the beam and required enormous sections, what is not the case in real life. Assign releases at the beam ends? In this case haw Etabs takes in consideration that in real life there are no released beam & column joints in monolithically poured structures?
I am sorry for long post.
Any input on these matters are highly appreciated.
Best regards.