rockman7892
Electrical
- Apr 7, 2008
- 1,156
What is typically viewed as best practice for combining control cables in UG conduit in Substations? Lets assume typical control cables consists of CT wiring, PT wiring, 125VDC control, 120VAC power, 48V control.
- Is it typical to combine CT wiring with other 125V DC control wiring?
- Is it typical to combine CT & PT wiring?
- Is it typical to combine 120VAC (or any AC power) with CT wiring or DC control?
- Is it typical to combine different voltage levels for DC voltages (IE 48V and 125VDC)?
I know that the NEC and other codes likely allow for combination of the above (IE 600V class wiring) so was looking for more of a "best practice" and reliability perspective.
Thanks
- Is it typical to combine CT wiring with other 125V DC control wiring?
- Is it typical to combine CT & PT wiring?
- Is it typical to combine 120VAC (or any AC power) with CT wiring or DC control?
- Is it typical to combine different voltage levels for DC voltages (IE 48V and 125VDC)?
I know that the NEC and other codes likely allow for combination of the above (IE 600V class wiring) so was looking for more of a "best practice" and reliability perspective.
Thanks