claytill
Geotechnical
- Jun 13, 2005
- 10
Background: I am overseeing a project in which we have encountered freezing air temperatures and recommended to our client that the imported fill must not contain frozen soil. The client decided to continue to immport frozen material and instructed us to continue with the 95 % compaction spec - my final report will qualify this. The future land use is unknown at this time and likely to be just landscaped. However, this can change as we all know.
Question: We plan to continue placing the frozen material and compacting to 95%, but I am still concerned with settlement issue. Does anyone know of any literature/paper that discusses these issues?? Any comments welcome.
Question: We plan to continue placing the frozen material and compacting to 95%, but I am still concerned with settlement issue. Does anyone know of any literature/paper that discusses these issues?? Any comments welcome.