Bahrain73
Civil/Environmental
- Mar 22, 2018
- 2
A very newbie question regarding compaction.
Basically we are doing a foundation for 5 floor building with basement. Piling was done now we are doing the pile caps and tie beams. Before we do the raft slab we have done the compaction for the tie beam and pile caps. The engineer on site stopped us as they said that compaction should be done for the whole area at once. If not the compaction of the raft slab can damage the integrity of the already compacted soil for tie beams and pile caps.
Would you agree with this ?
If so is there any standard or standard operating procedures you can refer me to stating the above ?
Thanks all
Basically we are doing a foundation for 5 floor building with basement. Piling was done now we are doing the pile caps and tie beams. Before we do the raft slab we have done the compaction for the tie beam and pile caps. The engineer on site stopped us as they said that compaction should be done for the whole area at once. If not the compaction of the raft slab can damage the integrity of the already compacted soil for tie beams and pile caps.
Would you agree with this ?
If so is there any standard or standard operating procedures you can refer me to stating the above ?
Thanks all