rlewistx
Structural
- Jun 21, 2003
- 98
I am working on designing a wall for a 20 ft. deep trench in an industrial building. The building is up and the slab in poured and now they need special equipment that needs a long deep trench. I was thinking about using soldier piles with tiebacks and wood lagging to shore the trench. Then put a concrete face in front of the soldier piles. I did a lot of this design work back in 1985 after getting out of college. Back then I had a Sr. engineer who guided me through the design. I remember quite a bit of it but I don't remember how to tie the concrete face into the tieback system so that when the wood lagging rots the concrete face holds back the soil.
Another question regards setting the piles in place. I need to visit the site but my gut feeling that a pile driver might not work. I was thinking initially of drilling holes, setting the pile and backfilling with very lean concrete. Then when the trench is excavated the lean concrete can be broken away to allow the wood lagging to be inserted.
I would appreciate any insight into solving this problem. Maybe my soldier pile solution isn't the best?
Thanks much!
Rich
Another question regards setting the piles in place. I need to visit the site but my gut feeling that a pile driver might not work. I was thinking initially of drilling holes, setting the pile and backfilling with very lean concrete. Then when the trench is excavated the lean concrete can be broken away to allow the wood lagging to be inserted.
I would appreciate any insight into solving this problem. Maybe my soldier pile solution isn't the best?
Thanks much!
Rich