Johnrmd
Civil/Environmental
- Nov 1, 2021
- 3
I have a 2way slab that is 11" thick and the formwork is a Single post System with a grid 6'x8' and I want to release the forms and leave the Post in place until the allowable Strength is achieved. Beside doing calculations for punch shear for the Steel post, what other calculations can I do that will allow me to give to the Structural Engineer so he can approve releasing the grid system (main beams and Secondaries) to approve early stripping of the system without releasing the post. Any advise and direction would help.
Thanks
John
Thanks
John