USFEngineer
Structural
- Dec 12, 2006
- 33
I have a project that we are currently working on in the construction phase. Several concrete compressive strength tests have come back well below our specified at 28 days. Most of them achieved the desired strength at or near 56 days and a couple of them never achieved design strength. For example at 28 days the average strength was about 1800 psi - 2200 psi. Specified was 3000 psi at 28 days.
My first question and probably the most important is what would be the proper way of handling such a situation? I have been asked if the concrete needs to be "ripped out". This seems a little harsh, are there any possible solutions?
Thanks in advance.
Andrew
My first question and probably the most important is what would be the proper way of handling such a situation? I have been asked if the concrete needs to be "ripped out". This seems a little harsh, are there any possible solutions?
Thanks in advance.
Andrew