Dennis59
Structural
- Dec 29, 2000
- 56
Back in Feb. '05 there was a thread entitled "Concrete Mix Design". (thread507-116513)
The question was, "Does anyone know if ACI specifically says what must be included in a concrete mix design submittal?"
Several replies were offered with people's individual experiences in this regard.
Member "jmiec" offered this:
"If you specified that the Contractor meet ACI 301, you can ask for Submission of data and test documentation on materials and mixture proportions under Article 6, Quality Assurance."
Back in July '03 I posted a question "Concrete specified via ACI 301" (thread167-63899) asking if anyone was actually using ACI 301 as ACI had originally intended it to be used. Judging by the text of ACI 301-99, paragraph F2, ACI intended that a design engineer could write a one page spec for all of Division 3 by simply citing ACI 301, and then adding whatever mandatory and optional requirements he/she decided to add.
Presumably then Contractors would go buy a copy of ACI 301 and red-line it with whatever mandatory and optional requirements the engineer indicated, and then that book would be the concrete spec for the job.
In my July '03 post I asked if any folks on this forum were actually specifying concrete this way. I would have to say that the response was "NO".
What is the situation now in 2006? Have any of you taken to using ACI 301 like this? If so, how's it working? If not, why not? It seems like ACI put a lot of effort into 301 and then no one's using it as ACI intended? It would seem that widespread use of ACI 301 in this fashion would be a good thing (for contractors, engineers and inspectors).
As for the question that was asked by thread507-116513, if we are using ACI 301 as ACI intended, then all of the submittal requirements are indeed already spelled out for us - and they are mandatory, not optional. I have ACI 301-99, and the concrete mix submittal requirements can be found at:
1.6.3.2.e
4.1.2.1
4.1.2.2
4.1.2.3
4.1.2.4
4.2.3.4.a
Most of these are included in the "Submittals Checklist" near the end of ACI 301.
Any comments you care to offer will be greatly appreciated.
The question was, "Does anyone know if ACI specifically says what must be included in a concrete mix design submittal?"
Several replies were offered with people's individual experiences in this regard.
Member "jmiec" offered this:
"If you specified that the Contractor meet ACI 301, you can ask for Submission of data and test documentation on materials and mixture proportions under Article 6, Quality Assurance."
Back in July '03 I posted a question "Concrete specified via ACI 301" (thread167-63899) asking if anyone was actually using ACI 301 as ACI had originally intended it to be used. Judging by the text of ACI 301-99, paragraph F2, ACI intended that a design engineer could write a one page spec for all of Division 3 by simply citing ACI 301, and then adding whatever mandatory and optional requirements he/she decided to add.
Presumably then Contractors would go buy a copy of ACI 301 and red-line it with whatever mandatory and optional requirements the engineer indicated, and then that book would be the concrete spec for the job.
In my July '03 post I asked if any folks on this forum were actually specifying concrete this way. I would have to say that the response was "NO".
What is the situation now in 2006? Have any of you taken to using ACI 301 like this? If so, how's it working? If not, why not? It seems like ACI put a lot of effort into 301 and then no one's using it as ACI intended? It would seem that widespread use of ACI 301 in this fashion would be a good thing (for contractors, engineers and inspectors).
As for the question that was asked by thread507-116513, if we are using ACI 301 as ACI intended, then all of the submittal requirements are indeed already spelled out for us - and they are mandatory, not optional. I have ACI 301-99, and the concrete mix submittal requirements can be found at:
1.6.3.2.e
4.1.2.1
4.1.2.2
4.1.2.3
4.1.2.4
4.2.3.4.a
Most of these are included in the "Submittals Checklist" near the end of ACI 301.
Any comments you care to offer will be greatly appreciated.