concreteworld
Civil/Environmental
- Jul 1, 2012
- 44
Hello Gentlemen,
We have a case where bottom 1 meter of concrete wall had late setting and did not achieve required strength at 28 days. Came out only 10% of fck. The bottom 5 meters is absolutely ok. Is there any quick method to remove the bottom 1 meter portion of concrete and replace with new concrete without affecting the stability of top 5meters of wall and such that both top and bottom repaired portion act monolithically.
Thanks in advance
We have a case where bottom 1 meter of concrete wall had late setting and did not achieve required strength at 28 days. Came out only 10% of fck. The bottom 5 meters is absolutely ok. Is there any quick method to remove the bottom 1 meter portion of concrete and replace with new concrete without affecting the stability of top 5meters of wall and such that both top and bottom repaired portion act monolithically.
Thanks in advance