SperlingPE
Structural
- Dec 27, 2002
- 591
I am in the process of designing the joint pattern for a manufacturing building.
I have located the control joints and construction joints and I am now considering whether to include an expansion joint. Right now the reinforcing (heavy mesh for the 6" slab) in the slab stop at the construction joints.
Generally, the slab is 6" thick, 80 feet wide, and 800 feet long. I say generally, because there is a 8" thick slab strip that is 450 feet long and 15 feet wide also.
There are the usual traffic aisles, manufacturing aisles, platforms, racks, crane columns, utility trenches scattered throughout the structure.
The building will be heated in the winter with no cooling in the summer.
The slab will be poured in the summer when the building is enclosed. Possible temperature at time of pour could be in the range of 80-100 degrees fahrenheit.
Questions
1. Is there a way to estimate the drying shrinkage of a slab?
2. Would you include an expansion joint(s)?
I have located the control joints and construction joints and I am now considering whether to include an expansion joint. Right now the reinforcing (heavy mesh for the 6" slab) in the slab stop at the construction joints.
Generally, the slab is 6" thick, 80 feet wide, and 800 feet long. I say generally, because there is a 8" thick slab strip that is 450 feet long and 15 feet wide also.
There are the usual traffic aisles, manufacturing aisles, platforms, racks, crane columns, utility trenches scattered throughout the structure.
The building will be heated in the winter with no cooling in the summer.
The slab will be poured in the summer when the building is enclosed. Possible temperature at time of pour could be in the range of 80-100 degrees fahrenheit.
Questions
1. Is there a way to estimate the drying shrinkage of a slab?
2. Would you include an expansion joint(s)?