I have a little spin to add to a standard concrete tank design. With the underground concrete tank I am working on, the contractor/timeline requires to form and pour the lid on the ground while working on the floor and walls. When the walls are complete with adequate cure time, the lid(s) would be craned on to the tank.
Can anyone recommend information on specifying lift loops and guidance on spacing and associated reinforcing details required for the lift?
The lid(s) also have openings of various sizes and arrangements to allow future mechanical replacement, ie pumps, etc.
Thanks.