Concrete Technology DOE method

Status
Not open for further replies.

sro2ck

Civil/Environmental
Jan 18, 2014
12
In DOE method,
if slump has been specified as 30mm. so, should i take (10-30)mm interval datas
Or
(30-60)mm interval datas for my calculations.
 
Replies continue below

Recommended for you

Also,for determining Maximum and minimum water content, specification table is given only for aggregates of 20mm Nominal Maximum
size.Can any one suggest where can i get specification table for aggregates of 40mm Nominal Maximum size.
 