Gebau
Structural
- Oct 20, 2010
- 1
I am designing a metal building foundation with a concrete "grade" beam at each column to resist the Outward Thrust forces imposed by the columns.
Just noticed ACI318-05 sect 12.5 requires Mechanical Splices for Tension Tie beams, but cannot find any definition of what constitutes a tie beam.
In this case, I have 2x the Area of Steel required and initially designed with staggered Class A Splices. Do I have to go to Mechanical Splices?
Just noticed ACI318-05 sect 12.5 requires Mechanical Splices for Tension Tie beams, but cannot find any definition of what constitutes a tie beam.
In this case, I have 2x the Area of Steel required and initially designed with staggered Class A Splices. Do I have to go to Mechanical Splices?