wcg89
Mechanical
- Jul 7, 2015
- 5
Tilt-up wall panel specs:
12'w x 24't x 6.5" thick
#4 @ 12"O.C. horizontally
#6 @ 10"O.C. vertically
The cut will be made on a panel along the North Wall of the building, there are 11 panels on this North end, the panel that will be cut is panel #5.
I should also mention that the North side of this building has two levels of tilt-up panels and this cut will be made on the top level.
I have the original plans for the building from the early 80's on PDF, but the design for the wall panel is pretty vague and the plans are hard to read as it is because the plans are old and whoever scanned them in long ago didnt do a very good job.
Each panel has three plates in them vertically along both sides, the panels are welded together at these plates.
Like I said the original plans are hard to read, but by observation of the building it seems that the wall panels are not holding up the roof of the building. There are steel I-beams at the corners and several cross members all the way around the building holding up the roof.
The cut will be a 55 1/4" sq. and 8' from the floor to the bottom of the hole.
As you can probably guess, I am concerned that once the hole is cut and there is that much rebar being cut out of the wall, that the wall will fail and buckle at the hole.
I am looking for guidance on how to ensure that this does not happen, at first I was just going to reinforce the opening with 3/16" thick angle iron, anchored to the wall on both sides and welded together inside the opening. Will this be enough? Do I just need to beef it up to thicker angle iron? Or should I run a couple of steel beams from the floor to the ceiling up the wall?
Thanks for any help!
12'w x 24't x 6.5" thick
#4 @ 12"O.C. horizontally
#6 @ 10"O.C. vertically
The cut will be made on a panel along the North Wall of the building, there are 11 panels on this North end, the panel that will be cut is panel #5.
I should also mention that the North side of this building has two levels of tilt-up panels and this cut will be made on the top level.
I have the original plans for the building from the early 80's on PDF, but the design for the wall panel is pretty vague and the plans are hard to read as it is because the plans are old and whoever scanned them in long ago didnt do a very good job.
Each panel has three plates in them vertically along both sides, the panels are welded together at these plates.
Like I said the original plans are hard to read, but by observation of the building it seems that the wall panels are not holding up the roof of the building. There are steel I-beams at the corners and several cross members all the way around the building holding up the roof.
The cut will be a 55 1/4" sq. and 8' from the floor to the bottom of the hole.
As you can probably guess, I am concerned that once the hole is cut and there is that much rebar being cut out of the wall, that the wall will fail and buckle at the hole.
I am looking for guidance on how to ensure that this does not happen, at first I was just going to reinforce the opening with 3/16" thick angle iron, anchored to the wall on both sides and welded together inside the opening. Will this be enough? Do I just need to beef it up to thicker angle iron? Or should I run a couple of steel beams from the floor to the ceiling up the wall?
Thanks for any help!