JT-1995
Structural
- Sep 26, 2022
- 36
In foundation construction (my cases are typically industrial and within existing facilities) I have formed the opinion that it is better to excavate a foundation, place reinforcement, and fill the entire excavation with specified concrete as opposed to a thinner structural section at the bottom of the excavation, cure, then form and pour a pier(s) to base plate elevation, cure, and then place compacted structural soil fill. The placed concrete is maybe 3-4 times more expensive per yard than soil (depending on location in the facility) but assuming the volume is not extraordinary I have convinced my self the time savings and quality control advantages make the concrete fill a better option. For consideration, say the bottom of a mat footing is 4ft below grade and the total dimension of the excavation is 20ft square. Hypothetically, we could design a 24" footing with say (4) 2ft pier(s) and backfill with soil (= 31yds concrete and 29yds compacted fill probably placed in 3 lifts) or using concrete fill we would end up with 60yds of concrete.
I would appreciate opinions on the above.
From a design perspective, As(min) becomes large in the thick footing and must be accounted for in the thick foundation design...correct?
Thanks
I would appreciate opinions on the above.
From a design perspective, As(min) becomes large in the thick footing and must be accounted for in the thick foundation design...correct?
Thanks