gringor
Mechanical
- Dec 12, 2017
- 4
building a 2 story waterfront home on Intracoastal in Florida. Most of the building pad is:
Stratum 1 - Loose light gray to dark brown fine sand to 2 to 4 ft below grade
Stratum 2 - dense cemented sand and shell to 9 to 12 ft below grade
Stratum 3 - refusal (presumed limestone, sandstone, or cemented coquina)
water was 3.5 ft below grade at test time (i suppose this varies with tide)
exception is a corner of the building pad that has a layer of very soft grey silt between 3 and 5.5 ft below grade. It spans 100 to 200 sq foot area of the building pad (estimated from digging test pits).
building pad will be raised a 3.5 over current grade to comply with BFE. Foundation is stem wall with overpour.
soils engineer is advising to remove silt, refill with clean compacted fill. General Contractor (GC) is saying its better to NOT remove the silt layer (because he says it can never be compacted as good as undisturbed state) and beef up foundation with extra steel and maybe some concrete/rebar poured down past the silt layer and on top of the cemented shell/sand. In his view doing anything is being over cautious because he thinks it is not enough silt to be concerned with. Architect and soil engineer dont like GC's beefed up foundation in that area idea, because of differential settling concerns. Soils engineer says clean fill replacing the silt can indeed be compacted adequately and will be just fine.
GC has got a years of "nuts and bolts" experience builing in this area (Florida) so I dont want to just discount his concerns. So Im just double checking with the experts here. Who is right? Would the above described silt layer come back to haunt me if I dont remove it? Or am I creating an unecessary problem by disturbing the soil to remove the silt layer?
Thanks in advance for any thoughts on the matter.
Stratum 1 - Loose light gray to dark brown fine sand to 2 to 4 ft below grade
Stratum 2 - dense cemented sand and shell to 9 to 12 ft below grade
Stratum 3 - refusal (presumed limestone, sandstone, or cemented coquina)
water was 3.5 ft below grade at test time (i suppose this varies with tide)
exception is a corner of the building pad that has a layer of very soft grey silt between 3 and 5.5 ft below grade. It spans 100 to 200 sq foot area of the building pad (estimated from digging test pits).
building pad will be raised a 3.5 over current grade to comply with BFE. Foundation is stem wall with overpour.
soils engineer is advising to remove silt, refill with clean compacted fill. General Contractor (GC) is saying its better to NOT remove the silt layer (because he says it can never be compacted as good as undisturbed state) and beef up foundation with extra steel and maybe some concrete/rebar poured down past the silt layer and on top of the cemented shell/sand. In his view doing anything is being over cautious because he thinks it is not enough silt to be concerned with. Architect and soil engineer dont like GC's beefed up foundation in that area idea, because of differential settling concerns. Soils engineer says clean fill replacing the silt can indeed be compacted adequately and will be just fine.
GC has got a years of "nuts and bolts" experience builing in this area (Florida) so I dont want to just discount his concerns. So Im just double checking with the experts here. Who is right? Would the above described silt layer come back to haunt me if I dont remove it? Or am I creating an unecessary problem by disturbing the soil to remove the silt layer?
Thanks in advance for any thoughts on the matter.