azogr
Structural
- Feb 21, 2007
- 59
I have been asked by a client to design a foundation for a building which will cover an existing structure (a concrete aggregate bin). The bin sits on a large mat foundation and the dimensions of this new building are very tight to the existing structure.
Before I had known that the existing foundation was so large I had sized footings which apparently will now interfere with the corners of the existing matt. The new building only has four columns. The contractor thinks this is a simple issue and wants me to simply put a large notch in my footing and tie into the existing matt.
I was going to resort to building a model in RISA to see how my new irregular footing and the existing mat footing would interact if knitted together. Is this overcomplicating the issue? I am interested to hear how others would approach this problem.
I also have a question about how they plan to tie the two foundations together. The contractor says that they just drill holes in the existing foundation and hammer in rebar that fits tight in the hole and then pour the new foundations around the bar. They claim that have done this for years and they do not use epoxy, grout or any other kind of bonding agent. Is this common? I plan to specify Hilti expoxy and whatever size rebar is required to meet the shear load.
Any thoughts or comments are greatly appreciated.
Thanks!
Before I had known that the existing foundation was so large I had sized footings which apparently will now interfere with the corners of the existing matt. The new building only has four columns. The contractor thinks this is a simple issue and wants me to simply put a large notch in my footing and tie into the existing matt.
I was going to resort to building a model in RISA to see how my new irregular footing and the existing mat footing would interact if knitted together. Is this overcomplicating the issue? I am interested to hear how others would approach this problem.
I also have a question about how they plan to tie the two foundations together. The contractor says that they just drill holes in the existing foundation and hammer in rebar that fits tight in the hole and then pour the new foundations around the bar. They claim that have done this for years and they do not use epoxy, grout or any other kind of bonding agent. Is this common? I plan to specify Hilti expoxy and whatever size rebar is required to meet the shear load.
Any thoughts or comments are greatly appreciated.
Thanks!