I'm going to break the connection specs and need forum members input for correct action, my problem is hereunder;
Production facility (Production separator) is having following specs (all piping associated with production separator is 300#), oil line upto skid is 300# and i want to tie-in with 150# existing facility. Shell I break the specs from the down stream of control valve or from the skid outlet.
Thanks
10815L
I'm going to break the connection specs and need forum members input for correct action, my problem is hereunder;
Production facility (Production separator) is having following specs (all piping associated with production separator is 300#), oil line upto skid is 300# and i want to tie-in with 150# existing facility. Shell I break the specs from the down stream of control valve or from the skid outlet.
Thanks
10815L